Silverado Park Signature Playground

Silverado Park Playground Photo

Additional project updates and information will be published on an on-going basis.

Latest Updates - September 2024

The Project team has finalized the designs for the Silverado Park Playground Project and has incorporated community feedback into the final design plans. The City has recently advertised the work for public bid and is currently evaluating General Contractor bids for responsiveness. After this process is completed, the City will make a recommendation to award a contract to the lowest, responsive, and responsible bidder. Construction is anticipated to start in early 2025. We want to express our gratitude to everyone who has provided feedback.

 
  • May 2024 Update

    The Silverado Park Playground Project has completed the Design and Permitting process and is moving forward with a competitive BID procurement process to select and hire a contractor to manage construction. More details of the BID can be found on Long Beach Buys. Construction is anticipated to begin in early 2025.

    Renderings of the project can be seen in the Project Information section below.

  • September 2023 Update

    The City of Long Beach hosted a community meeting in May 2023 at the Silverado Park Community Center to discuss project updates and next steps for upcoming improvements. The project team is currently revising the design based on the feedback from the community.

  • May 2023 Update

    The City of Long Beach invites the community to learn about the Silverado Park Playground Project on Wednesday, May 31, 2023 at 5:30 p.m. at the Silverado Park Community Center (1545 W. 31st St.). Join us to hear about project updates and next steps for the upcoming improvements. 

Estimated Timeline

*Timeline is set barring unforeseen weather changes or other circumstances

Community Engagement Spring - Summer 2023
Permitting / Regulatory Approvals Fall 2023 - Winter 2024
Detailed Design and Construction Documentation Fall 2023 - Spring 2024
Bid / Award / Contract Procurment  Summer - Fall 2024
Begin Construction  Early 2025

Project Information

The Silverado Park Signature Playground Project will focus on replacing the existing playground facilities and site furnishings. Designs will include new and exciting play elements in two distinct play areas: 2-5 year olds and 5-12 year olds. The playground colors and theme will also complement the existing mural at Silverado Park.

The project aims to:

  • Provide playground improvements to serve a high-need community
  • Increase the useful life of the facility
  • Provide an inviting environment for the community
  • Address ADA accessibility

+Click Images Below for Larger View

Silverado Park Playground Rendering 1

Silverado Park Playground Rendering 2

Silverado Park Playground Rendering 3

Project Funding

Former U.S. House Representative Lowenthal generously secured $1.5 million in federally earmarked funds from the U.S. Department of Housing and Urban Development's Community Development Fund. In addition, $700,000 Measure A Funds have also been allocated to the project. Together, these two funding sources will go towards a full reconstruction of Silverado Playground, including new play features, benches, picnic tables, and ADA site improvements.

Project Contact

Justin Beck, Capital Projects Coordinator
(562) 570-6964, parkscip@longbeach.gov

More Information

Silverado Park Playground Project Community Meeting Presentation - May 31, 2023