Silverado Park Signature Playground
Background
The Silverado Park Signature Playground features new, inclusive play equipment and site furnishings, designed with accessible pathways and ADA-compliant amenities. The playground encourages sensory, physical, and imaginative play, with two distinct areas for preschoolers (ages 2–5) and school-age children (ages 5–12). Inspired by the park’s mural We Are the Seeds by Mer Young, the design will reflect its vibrant colors and theme.
This project is part of the Elevate ’28 Infrastructure Investment Plan, a historic initiative dedicated to enhancing Long Beach parks, community facilities, mobility access, and streets. Learn more at lbelevate28.com.
Timeline
| Community Feedback | Spring - Summer 2023 |
| Permitting and Regulatory Approval | Fall 2023 - Winter 2024 |
| Design and Construction Documentation | Fall 2023 - Spring 2024 |
| Bid, Award and Contract Procurement | Summer - Fall 2024 |
| Construction | March 2025 - September 2025 |
| Project Completion | September 2025 |
Objectives
- Create an inviting environment for the community
- Extend the useful life of the facility
- Address ADA accessibility issues
- Improve access to City resources
- Enhance visitor experience
Proposed Features
- New, level concrete at the gym’s entrance to improved accessibility
- ADA-compliant amenities, including an accessible pathway with a ramp to play equipment and accessible picnic tables
- ADA-compliant play equipment for sensory, physical, and imaginative play
- Rubberized playground surface for added protection
- Additional benches and picnic tables in the playground area
Project Funding
The Silverado Park Signature Playground was funded by $1.5 million from the U.S. Department of Housing and Urban Development's Community Development Fund, $200,000 of Measure A funds, and $750,000 from the Elevate 28 Infrastructure Investment Plan.
To learn more about Elevate ’28 and the historic infrastructure investment currently underway in the City of Long Beach, visit lbelevate28.com.
More Information
- Silverado Park Signature Playground Timeline Display Board
- Silverado Park Signature Playground Project Details Display Board
- Silverado Park Signature Playground Project Features 1 Display Board
- Silverado Park Signature Playground Project Features 2 Display Board
Latest Updates
The Department of Public Works and Parks, Recreation and Marine to celebrated the grand opening of the Silverado Park Signature Playground project on Friday, September 12. Attendees received a first look at the renovated playground, designed to provide even more opportunities for play, relaxation and community gatherings.
The Departments of Public Works and Parks, Recreation and Marine celebrated the groundbreaking of the Silverado Park Signature Playground on March 1, 2025. 


- Work hours are scheduled to take place Monday through Friday between 7 a.m. and 4 p.m.
- The playground will remain closed during construction.
- The gym will remain open and operational for most of the construction. There will be a closure of up to two weeks for concrete improvements at the entrance, with advanced notice and signage provided prior to closure.
- Street parking will be available for the duration of construction.
- Efforts will be made to limit disruptions during scheduled park activities, however there may be minor impacts.
- For your safety, please avoid all construction areas.
The City of Long Beach invited the community to learn about the Silverado Park Playground Project on Wednesday, May 31, 2023, at 5:30 p.m. at the Silverado Park Community Center (1545 W. 31st St.). Attendees heard about project updates and next steps for the upcoming improvements.