Home Public Works Projects and Programs Scherer Park Community Center

Scherer Park Community Center

Scherer Park Community Center with new interior ceiling tiles

Additional project updates and information will be published on an on-going basis.

Updates

June 2024

The City’s Contractor, MIK Construction, began Construction in October 2023. Construction activities are nearly complete.

Work completed includes:

  • Installation of new energy efficient windows and security doors.
  • New interior ceiling tiles, electrical, and energy efficient HVAC system.
  • Installation of new restroom partitions, lighting, and drinking fountain.
  • New exterior paint and colored graphics.
  • Improvements to accessible parking and path of travel around the Center.

Final Construction activities are expected to be completed mid-July. Please stay tuned for updates on a Grand Opening Ceremony anticipated to be scheduled in August of this year!


Estimated Project Timeline

*Construction timeline is set barring unforeseen weather changes or other circumstances.

Planning February 2021 - July 2021
Design & Permitting July 2021 - January 2023
Bid & Award January 2023 - June 2023
Construction October 2023 - July 2024

Project Information

The Scherer Park Community Center Project will renovate the interiors and exteriors of both the community center and park restroom. There will be enhancements made to the stall partitions, electrical, exterior and interior paint, HVAC, and signage. The parking lot and path of travel will also be improved for better ADA access throughout the area.

The community center is a frequently used space and these improvements will enhance the space for after school programming and summer camp access while making the center more energy efficient.

Project Funding

This project is currently funded by local and county Measure A along with AB32.

Project Contact

Justin Beck, Capital Projects Coordinator
(562) 570-6964, parkscip@longbeach.gov