Ramona Park Signature Playground Project
Click here for project updates.Background
The Ramona Park Signature Playground project marks a significant upgrade to the park since its last renovation in 1997. The new design features inclusive play equpiment for children of all ages, along with shade structures, misters and improved seating areas, creating a more welcoming, engaging, and accessible space for families.
This project is a part of the Elevate ’28 Infrastructure Investment Plan, a historic initiative dedicated to enhancing Long Beach parks, community facilities, mobility access, and streets. Learn more at lbelevate28.com.
Timeline
| Planning | July 2022 – October 2022 |
| Design and Permitting | October 2022 – April 2024 |
| Bid and Award | February 2024 – December 2024 |
| Construction | February 2025 – September 2025 |
| Project Completion | October 2025 |
Objectives
- Create an inviting environment for the community
- Extend the useful life of the facility
- Enhance accessibilty with ADA-compliant amenities
- Improve access to City resources
- Enhance visitor experience
- Reduce heat impacts with cooling features
Proposed Features
- ADA-compliant amenities such as play equipment, pathways, and parking stalls
- Rubberized surfacing to help improve safety and support access to play equipment for people using mobility devices
- Inclusive and accessible play equipiment for sensory, physical, and imaginative play
- Two new ADA picnic tables
- Transfer stations for mobility devices throughout the play area
- Misters for cooling that are designed to be operated by individuals in mobility devices
- Hydration stations designed to meet ADA standards
- Shade structures and fog mister
- Enhanced landscaping with additional trees for shade
Project Funding
The project was funded by a $1,500,000 grant from California State Parks, a $550,000 Community Development Block Grant from the US Department of Housing and Urban Development, and $650,000 in Measure A funding.
Total estimated project cost is $2.7 million.
More Information
- Ramona Park Playground Community Meeting - March 16, 2023
- Ramona Park Playground Project Details Display Board
- Ramona Park Playground Project Features 1 Display Board
- Ramona Park Playground Project Features 2 Display Board
- Ramona Park Playground Project Timeline Display Board
Project Updates
October 2025
The Department of Public Works and Parks, Recreation and Marine hosted a grand opening ribbon-cutting ceremony on Saturday, October 25 at the newly renovated Ramona Park Signature Playground.
March 2025
On Mar. 28, 2025, the City celebrated the construction start of the project.
![]() |
![]() |
![]() |
![]() |
January 2025
The Ramona Park Signature Playground project is set to kick off in February 2025!
Planned improvements include:
- ADA-compliant amenities
- Shade structures and fog misters
- Enhanced landscaping with additional shade trees
- Play equipment for sensory, physical, and imaginative play
- Safety surfacing with shock-absorbing material
- Upgraded seating areas
Residents Should Note:
- Work hours are scheduled to take place Monday through Friday between 7 a.m. and 4 p.m.
- The Ramona Park Playground will remain closed during construction.
- The Ramona Park facility will remain open and operational during construction. Visitors may continue to access the building through the East 65th Street entrance.
- The southern parking lot off East 65th Street will remain closed during construction to allow for equipment staging and restriping. Street parking and the northern parking lot will be available.
- Efforts will be made to limit disruptions during scheduled park activities, however there may be minor impacts.
- For your safety, please avoid all construction areas.
- Construction is expected to be completed by Fall 2025, pending weather or unforeseen circumstances.
- The City’s contractor, SJD&B Construction, will oversee the project.
We appreciate your patience and cooperation as we work to create more accessible and community-friendly spaces. For questions, please email us at parkscip@longbeach.gov or call the Construction Manager, Steve Patterson at 949-753-7333.