Drake Park Community Center Improvements

Click here for project updates.

Project Information

The Drake Park Community Center Improvements project is a multi-phase effort to modernize the facility, address aging infrastructure, and ensure it continues to meet the needs of the community. The project was designed to be implemented in three phases to minimize disruptions while allowing critical upgrades to be completed in a strategic and efficient manner.

Phase I addressed major HVAC system improvements to enhance building performance and visitor comfort, followed by Phase II, which focused on rebuilding the exterior restrooms. Phase III will complete the project with comprehensive interior and exterior renovations that improve the overall functionality, accessibility, and usability of the community center. Together, all three phases represent the significant investment in the long-term sustainability and service capacity of this important neighborhood facility. 

This project is part of the Elevate '28 Infrastructure Investment Plan, a historic initiative dedicated to enhancing Long Beach parks, community facilities, mobility access and streets. Learn more at lbelevate28.com.

Estimated Project Timeline

Phase I Construction Start October 2023
Phase I Construction End April 2025
Phase II Construction Start October 2023
Phase II Construction End July 2025
Phase III Construction Start February 2026
Phase III Construction End November 2026
Project timeline is set barring weather delays and other unforeseen circumstances

Objectives

  • Improve visitor experience
  • Improve infrastructure quality

Project Features

  • New finishes (lighting, ceiling tiles)
  • Restroom and kitchen remodel
  • New furniture
  • New gender-neutral restroom
  • New office area

Project Funding

The Drake Park Community Center Improvements project is currently supported by Measure A, Measure A Bond, and AB32 funds. .              
           