Davies Boat Launch Facility Improvements
Additional project updates and information will be published on an ongoing basis.
Click here for project updates.
Background
The Davies Boat Launch Facilities Improvements project focuses on revitalizing one of the city's primary waterfront recreation destinations. The site plays an important role in supporting public access to coastal activities and serves a wide range of visitors including boaters and community members.
Over time, the facility has experienced wear and aging infrastructure, highlighting the need for a comprehensive effort to enhance its overall condition, safety, and functionality. This project represents a long-term investment in maintaining the sites role as a reliable and accessible recreational asset, while supporting continued public use enjoyment of the waterfront.
Timeline
| Design & Permitting | Spring 2019 - Summer 2025 |
| Bid & Award | Fall 2025 - Winter 2026 |
| Construction Start | April 2026 |
| Project Completion | Early 2027 |
Project timeline is set barring weather delays and other unforeseen circumstances.
Objectives
- Enhance boater safety
- Improve facility functionality and user experience
- Increase operational efficiency
- Extend the useful lifespan of waterfront infrastructure
Project Features
- Launch ramp replacement
- Parking lot pavement renovation and restriping
- Modern Restroom building
- Entrance gate & kiosk replacement
- Trash enclosures
- Boat washing station and token machine
- Sand-oil separator
- Fish cleaning station
- EV charging stations
- Electrical distribution system
- Site signage
- Improved parking lot lighting
- Accessibility enhancements to parking and pedestrian pathways
Project Funding
This project is supported with Tidelands funds, Marina funds and grants from the Division of Boating and Waterways.
More Information
Davies Boat Launch Facility Improvements Project Presentation - March 9, 2023
Project Updates
In July 2026, the contractor made significant progress installing electrical infrastructure including all conduit and risers to the light poles and feed panels. The contractor completed asbestos abatement of the demolished light pole foundations and piping. Due to changes in the new restroom location, survey was verified towards the end of the month. The contractor’s surveyor set out stakes for the new curb and gutter alignment, light pole foundations, and restroom.
In June 2026, the contractor made significant progress on the demolition of the site. The contractor demolished the upper 30-foot section of the concrete boat launch ramp, existing curb and gutter. The new sand-oil interceptor has been installed including the waste line to the outlet. Trenches were also dug up for electrical and water lines. The contracotr also improved the revetment along the south side of the project with imported rocks and repurposed concrete material from the project.
Visit the launch ramps webpage to view a list of alternative boat launch options in the city of Long Beach.
The project team is committed to moving forward with a design that satisfies both the City's standards and approved project budget. Stay tuned for updates on when the project will be re-bid.
On March 9, 2023, a project update presentation was given to the Marine Advisory Commission.
Contact
For questions about this project, please contact tidelandscip@longbeach.gov.