- City Officials
- Mary Zendejas1st District
- Cindy Allen2nd District
- Kristina Duggan3rd District
- Daryl Supernaw4th District
- Megan Kerr5th District
- Suely Saro6th District
- Roberto Uranga7th District
- Tunua Thrash-Ntuk8th District
- Dr. Joni Ricks-Oddie9th District
- Dawn McIntoshCity Attorney
- Laura L. DoudCity Auditor
- Doug HaubertCity Prosecutor
- Tom ModicaCity Manager
- Monique DeLaGarzaCity Clerk
- Services
- Businesses
- Residents
- Visitors
- Departments
- Jobs
Mayor
City Council
City-Wide Elected Officials
Appointed Officials
Departments
IB-001 Code Modification and Alternative Method Bulletin

Revised Jan. 2025
I. Application
The Application must be completed by the petitioner (which may be the building owner or company officer, architect, engineer, etc.) and signed by the building owner or company officer. For Applications that are classified as Category 1 (see Section VI), signature from the petitioner in lieu of the building owner or company officer may be acceptable. Where multiple issues exist, a separate form may be submitted for each issue. This may permit approval of certain items in the event it is necessary to deny one or more issues.
II. Making the Request
The request portion of the Application must contain a clear statement of the issue(s) that the Building Official and/or Fire Marshal is(are) requested to address. The section(s) of the applicable code or standard that is the subject of the appeal must be cited. The issue(s) may be an interpretation or application of a code provision or a finding on the equivalency to code requirements of alternative materials, design and methods of construction and equipment.
For projects that are in high-rise buildings, Group A, E, H, I, L and R occupancies and other applications listed in the Code regulated by the Office of the State Fire Marshal, the Fire Prevention Bureau’s input will be required for request related to fire-life safety requirements.
The Application shall be submitted along with a request letter. The request letter shall describe the scope of the project, elaborate on the reason, and justification for considering the request. In addition, any substantiating and supporting documents, details, or plans must be included with the completed Application. An initial non-refundable filing fee to review the Application shall be collected when the Application packet is submitted. The request letter shall be addressed to:
-
Building Official; Community Development Department; Building and Safety Bureau
AND/OR
-
Fire Marshal; Fire Department; Fire Prevention Bureau
III. Justification or Finding of Equivalency
The justification portion of the Application and the submitted request letter must state the basis for the request and substantiate the claim of impracticality or hardship for the purpose of code modification or finding of equivalency to code requirements for the purpose of proposed alternative materials, design and methods of construction and equipment. Furthermore, a registered design professional licensed in the State of California must justify the Application that involve issues related to fire-life safety or structural design in the request letter. LBMC §18.03.060.C authorizes the Building Official to require the submission of test data as proof of compliance at the Applicant’s expense whenever there is insufficient evidence of compliance with any of the provisions of this title or evidence that any material or construction does not conform to the requirements of this title. Plans submitted in support of the request must clearly indicate the location, nature, extent, and details of the subject of the appeal. Plans submitted must be of sufficient size to be suitable for filing and distribution and should be no smaller than 8.5” x 11” or no larger than 11” x 17” in size.
Code Modification
The requirements and prerequisites for granting a modification are enumerated in LBMC §18.03.050.A. This section provides in pertinent part as follows:
“Whenever there are practical difficulties involved in carrying out the provisions of this title, the Building Official shall have the authority to grant modifications for individual cases, upon the application of the owner or owner's representative, provided the Building Official shall first find that special individual reason makes the strict letter of this title impractical and the modification is in compliance with the intent and purpose of this title and that such modification does not lessen health, accessibility, life and fire safety, or structural requirements.”The justification given must specifically address that there are practical difficulties involved, a special individual reason must exist, and fire protection or structural safety are not diminished for the Building Official to consider granting a modification. The details of any action granting modifications shall be recorded and kept on file with the Bureau.
Alternative Materials, Design and Methods of Construction and Equipment
The requirements and prerequisites for granting a request for alternative materials, design and methods of construction, and equipment are enumerated in LBMC §18.03.060.A. This section provides in pertinent part as follows:
“The provisions of this title are not intended to prevent the installation of any materials or to prohibit any design or method of construction not specifically prescribed by this title, provided that any such alternative has been approved. An alternative material, design or method of construction shall be approved where the Building Official finds that the proposed design is satisfactory and complies with the intent of the provisions of this title, and that the material, method or work offered is, for the purpose intended, at least the equivalent of that prescribed in this title in quality, strength, effectiveness, fire resistance, durability and safety. The Building Official shall require that sufficient evidence or proof be submitted to substantiate any claims that may be made regarding its use.”It is prudent and proper for the Code to accommodate new technologies that were not considered in the formulation of prescriptive requirements. Indeed, a failure to do so would constitute an arbitrary prohibition of new products or methods without due consideration of merit. The justification or finding of equivalency given must specifically address the cited criteria (i.e., quality, strength, effectiveness, fire resistance, durability and safety). Additional information substantiating claims of equivalence such as code analyses, test reports, engineering analysis as well as other background information may be compiled in a report used as a part of the justification. Copies of documents, in part or in their entirety, referenced in the reports that are not commonly available may need to be provided.
IV. Rejection of Application
V. Processing Time and Deadlines
VI. Fees
- Category 1: The minimum initial filling fee is based on one hour of review time and will be charged for issues of minimal complexity and/or have been evaluated frequently on other cases. Surcharges apply and will be added to the filing fee.
- Category 2: The minimum initial filling fee is based upon three hours of review time and will be charged for issues of moderate complexity and/or have been evaluated infrequently. Surcharges apply and will be added to the filing fee.
- Category 3: The minimum initial filling fee is based upon five hours of review time and will be charged for issues of higher complexity and/or have not been evaluated previously. Surcharges apply and will be added to the filing fee.
Development Permit Center staff will determine the initial filing fee category. If a second opinion is requested, please ask for a supervisor to assist in this determination. Where the Fire Prevention Bureau’s input is required (see Section II), an additional review fee will be collected and paid with the Application submitted.
VII. Approval of Denial of Request
If the Building Official and/or Fire Marshal denies the request, the Applicant will be notified in writing of the reasons for the disapproval. Applicant wishing to appeal the decision of the Building Official and/or Fire Marshal may do so by applying for consideration by the Board of Examiners, Appeals, and Condemnation. Please refer to the “Appeal to the Board of Examiners, Appeals and Condemnation” Application on the Building and Safety Applications and Forms webpage. A record of the denial will be maintained in records associated with the project or applicable permit.
VIII. Expiration of Request
IX. For Additional Information
Additional information regarding the process of requesting code modification, the use of alternative materials, design and methods of construction and equipment or for submitting to the Board of Examiners, Appeals, and Condemnation may be obtained by contacting the Development Permit Center at 562.570.7648. Alternatively, the information or applications may be obtained on the Building and Safety Bureau webpage.
Helpful Links
Building & Safety Bureau
| M: | 8:00 AM - 4:00 PM |
| T: | 8:00 AM - 4:00 PM |
| W: | 9:00 AM - 4:00 PM |
| TH: | 8:00 AM - 4:00 PM |
| F: | 8:00 AM - 4:00 PM |
The Permit Center is closed daily for lunch from Noon to 1 p.m.
411 West Ocean Blvd., 3rd Floor
Long Beach, CA 90802
562.570.LBCD (5223)