Home » District 5 » News » Long Beach Energy Resources Pipeline Replacement(3)
LBER Pipeline Project

LBER Pipeline Replacement Project on Spring & Palo Verde

Release Date: 2018-11-05

In mid-November Long Beach Energy Resources (LBER), formerly known as Long Beach Gas & Oil, will officiall start work on a pipline replacement project near Spring St. and Palo Verde Ave. This necessary work will ensure gas distribution facilities continue to function at high standards of safety, reliability and efficiency. Project details are as follows:
  • Location: Spring Street (from Woodruff Ave. to Palo Verde Ave.) and Palo Verde Ave. (from Spring St. to Willow St.)
  • Projected Start Date: January 2, 2019
    (Changed from orginal start date of 11/19/2018)
  • Work Hours: 7:00 AM to 5:00 PM
  • Estimated Duration of Project: 9 weeks
Any questions or concerns may be directed to Jeff Ostrin, City Superintendent of Engineering at 562-570-2031. Or for 24/7 emergency response, call 562-570-2140.