Integration Calendar

To print this page, click the Print button to the right first.

Revised 6/20/08

Category

Major Goal

Action

Lead

Target Date/
Completed

TrainingTeam TrainingResource Center and Front Desk will be closed; No LCT MeetingChampions6/24
FacilitiesFinalize First Floor LayoutProvide FeedbackChampions6/25
FacilitiesFinalize First Floor LayoutMake decision on final layoutLeaders6/25
MeetingsPartner MeetingInform partners of the integration process and their involvement, and present MOUTBD6/25
ProcessAdd Draft DirectiveReview CommentsDawn6/25
TrainingTraining on ACES SchedulingTrainingMary6/25
Customer SatisfactionRevisit ProcessDetermine data collection and sharing processJP/DawnTBD
FacilitiesTenant ImprovementsProcure contractorGary/MeluTBD
ProcessDetermine Supportive Service Dissemination and Tracking ProceduresPolicy revision to incorporate into VOSMelu/SubgroupTBD
ProcessDetermine Supportive Service Dissemination and Tracking ProceduresDetermine voucher dissemination and tracking proceduresMelu/SubgroupTBD
ProcessDetermine ITA Tracking ProceduresDetermine procedure for tracking and communicating ITA expenditures in VOS, etc.Melu/SubgroupTBD
Quality ImprovementDetermine SystemImplement CQI process in support of continuous learning and improving SI processesTBDTBD
StrategyPerformance Mgt/Network Scorecard UpdateUpdateDawnTBD
TrainingAll Team TrainingConduct Overview Session - update on Integration for staffChampionsTBD
ProcessDefine Case ManagementDiscussionLCTOn-going
ProcessProduct BoxUpdateSusanOn-going
VOSEstablish VOS Case Note TemplatesDetermine Lead and deadlineLCTOn-going
VOSVOS Admin Module Set-upDetermine Lead and deadlineLCTOn-going
VOSEligibility/Data Mgt. VOS Transition PlanPresent draftDawnOn-going
VOSVOS-JTA Connectivity etc.UpdateDawn/JPOn-going
VOSVOS TrainingWebinars on-goingGSI/Susan/
Dawn
On-going
VOSVOS 9.1 Converstion - Full Case Management Plan: begin UAT testing on 5/27. Conversion 6/5-6/6Employment Specialists and Resource Center Staff begin to implement to identify glitches. Report glitches to Susan/Dawn/GSISusan/DawnOn-going

Completed Goals

CommunicationsPartner MeetingSet DateLeadershipX
CommunicationsCustomer CommunicationsDistribute - handout, marquee, webKathyX
CommunicationsDetermine regular meeting day and timeSchedule Leadership/Champions Team (LCT) meetings for next 6 weeksKathyX
CommunicationsInternal CommunicationsTimeline, Q&A, and vocabulary page developed, approved by LCT and posted on webKathyX
CommunicationsCustomer CommunicationsDraft customer notice message for approvalKathyX
CommunicationsDiscuss and Finalize Procedures ManualTable of ContentsKathyX
FacilitiesFinalize First Floor LayoutMake decision on final layoutLeadershipX
FacilitiesFinalize First Floor LayoutProvide feedbackChampionsX
MarketingCustomer Messaging/SignageHandout, Marquee, WebKathyX
MarketingLogosFinalize layout of PGWIN and EDD logos togetherKathyX
MarketingStickersFinalize design for stickers to place on existing Scan CardsSusanX
MeetingsAll-Staff Meeting AgendaCreate agenda for the all-staff meeting on 6/18KathyX
MeetingsAll-Staff MeetingStaff will be given updates from each Team Leader and questions will be answeredLCTX
MeetingsPartner MeetingFoodSuzanneX
ProcessDiscuss Practice RunSet DateAllX
ProcessHandoff Procedures: Skills and Solutions TeamsDiscussionLCTX
ProcessFinalize Welcome Team functional descriptionsUpdate and refine position descriptions and report to LCTSusanX
ProcessFinalize Solutions Team functional descriptionsUpdate and refine position descriptions and report to LCTCarlaX
ProcessFinalize Skills Team functional descriptionsUpdate and refine position descriptions and report to LCTAlisa/DorothyX
ProcessFinalize Product Team functional descriptionsUpdate and refine position descriptions and report to LCTKathy/SusanX
ProcessFinalize functional descriptionsPlace on web & wikiPeterX
ProcessFinalize Welcome Team customer flow chartsUpdate and refine flow charts and report to LCTSusanX
ProcessFinalize Solutions Team customer flow chartsUpdate and refine flow charts and report to LCTCarlaX
ProcessFinalize Skills Team customer flow chartsUpdate and refine flow charts and report to LCTAlisa/DorothyX
ProcessFinalize team customer flow chartsPlace on web & wikiPeterX
ProcessHandoff Procedures: WelcomeWelcome TeamSusan/DorothyX
StaffingStaff notified as to team assignmentsLCTX
StaffingStaffing/Supervising Roles and ResponsibilitiesBegin DiscussionAllX
TrainingProcedure ManualHand out to staff at all-staff meetingKathyX
TrainingStaff DevelopmentSchedule Team Building Workshops Two four-hour sessions: 5/7, 5/8Gary/MeluX
TrainingStaff DevelopmentTeam Building Workshops Scheduled Two four-hour sessions: 5/7, 5/8MeluX
TrainingTraining on the benefits and importance of standardized Assessment ToolsScheduled training dateDorothyX
TrainingVOS Clinic HourMove administrative and implementation decisions alongSusanX
VOSVOS Go-live(System Down 6/5, 6/6)Susan/DawnX
VOSVOS TrainingSchedule in-house with Geographic SolutionsMeluX
VOSVOS Data ResearchResearch maximum, minimum, and average distinct users. Report results to LCTGloria/SusanX
VOSDecision reached on VOS modules to be developmedLeadership team and Susan have conference with vendor to decide on modulesCherie/GaryX
VOSVOSContract negotiatedGaryX